Concrete › Concrete footing calculator
Concrete footing calculator: how much concrete for a footing in cubic yards and bags?
Enter the building length and width for a continuous footing around a house or garage, a straight run for a wall or thickened edge, or the size and count of pad footings, then the footing width and thickness from your plans, and get the concrete to order in cubic yards, the ready-mix quantity in quarter-yard steps, and bags in four sizes, with the IRC 2021 footing minimums checked as you type. Free, no signup, printable.
Footing concrete = run in feet × width in inches ÷ 12 × thickness in inches ÷ 12, then ÷ 27. The default 30 × 20 ft building with a 16 × 8 in footing is 2 × (30 + 20) = 100 linear ft along the footing centreline; 100 × 1⅓ × ⅔ = 88.89 cubic feet, 3.29 cubic yards in the trench, and with the 10 percent waste the headline reads 3.62 cubic yards to order: a ready-mix order of 3.75 cu yd in quarter-yard steps, or 163 bags of 80 lb mix. The hand formula below prints every step so a supplier's figure can be checked against it.
The calculator works the volume side of a footing: run, section, waste, bags, ready-mix. It does not size the footing for you; the width comes from your approved plans or from IRC 2021 Table R403.1(1), printed in full below, and the depth below grade comes from your frost line, not from any calculator. For a post in a hole or a sonotube use the post hole concrete calculator; for the size of a deck post footing the deck footing size calculator; for a slab on top of the footing the concrete slab calculator; for the job-by-job answer to how much concrete a footing or a post takes, concrete for footings and posts.
How to use this concrete footing calculator
Footing layout has three settings and each one changes the inputs. Continuous footing around a building takes the building length and width in feet and inches, 30′ 6″ or 30.5, and works out the run itself as 2 × (length + width); the measurement is along the centreline of the footing, not the outside face of the wall, and a note under the result prints the arithmetic so the corner count can be seen. Straight run takes one length for a wall footing, a garage-door thickened edge, an interior bearing-wall footing or a trench you have already measured. Pad / isolated footings takes a pad length and width in inches, the count, and no width field, because a pad has no run.
Footing width is the width of the concrete section in inches and defaults to 16; the help text under it says where the number comes from: your approved plans, or Table R403.1(1) for your soil bearing value and number of storeys. The tool does not derive it, on purpose, and warns below 12 in because the code tabulates nothing narrower for a light-frame building. Footing thickness is the depth of the concrete itself, default 8 in, and warns below the 6 in minimum of R403.1.1; it is not the depth of the excavation, which is a frost-line question the depth section takes up. Bag size picks which pre-mix row leads the result, and Waste allowance defaults to 10 percent, which is about right for a formed footing and on the low side for one poured to the trench walls.
| Row | What it is | Waste inside? |
|---|---|---|
| Concrete needed | Cubic yards for the run or the pads, with the waste percentage added; the headline | Yes |
| Ready-mix order (¼ yd steps) | The headline rounded up to the next quarter yard, the way a plant takes an order; the row appears only at half a yard and above | Yes |
| 80 lb bags | Bags of the size you picked for the waste-inclusive volume, rounded up; the four-size table below the result repeats it for 80, 60, 50 and 40 lb | Yes |
| Cubic feet / cubic metres | The same volume in the two other units, waste included | Yes |
| Footing run | Linear feet of footing: 2 × (length + width) for the perimeter layout, your figure for a straight run; not shown for pads | No |
| Each pad, before waste | One pad's own volume in cubic yards, geometry only, so the pad count and the waste can be checked separately | No |
| Trench cross-section | Width × thickness in square feet; multiply by any run to get cubic feet without the tool | No |
What the calculator warns and notes
Two warnings. A thickness under 6 in prints the R403.1.1 minimum; a width under 12 in on the perimeter and run layouts prints that Table R403.1(1) tabulates no footing narrower than that for light-frame construction and sends you back to the plans. Neither warning blocks the result, because a garden wall or a fence footing outside the code's scope can legitimately be smaller; the numbers still print, with the code figure beside them.
Three notes follow every result. The first says that depth below grade is set by the local frost line under R403.1.4.1 and is never less than 12 in below the undisturbed ground surface under R403.1.4, and that the thickness field is the concrete section, not that depth. The second is the projection rule from R403.1.1: the footing must stand past the face of the wall or column above it by at least 2 in and by no more than its own thickness, so a 16 in footing under an 8 in wall projects 4 in each side and passes at any thickness, while a 24 in footing only 6 in thick under the same wall projects 8 in and fails it. The third, on the perimeter layout, prints the run: 2 × (30.0 + 20.0) = 100.0 linear ft, corners counted once.
How to calculate concrete for footings by hand: run × width × thickness ÷ 27
Step one, the section. Width and thickness are in inches on every set of plans, so convert both to feet by dividing by 12, then multiply: 16 ÷ 12 × 8 ÷ 12 = 1⅓ × ⅔ = 0.89 square feet of cross-section, the figure the tool prints as the trench cross-section. If you would rather stay in inches, multiply width by thickness by the run in inches and divide by 1,728 for cubic feet or by 46,656 for cubic yards, since 12³ = 1,728 and 1,728 × 27 = 46,656: 16 × 8 × 1,200 ÷ 46,656 = 3.29 cubic yards, the same answer.
Step two, the run. For a continuous footing the run is the perimeter measured along the footing's centreline, 2 × (length + width), and it is 100 ft for a 30 × 20 ft building whichever way the corners are read, because each corner belongs to two sides once. Measured instead around the outside face of a 16 in footing the same building is 2 × (31.33 + 21.33) = 105.33 ft, which orders 3.81 yards instead of 3.62; measured around the inside face it comes up short by the same margin. Interior bearing-wall footings and garage-door edges are added as straight runs. For pads there is no run: length × width × thickness, all in feet, times the count.
Step three, the yards. Cubic feet ÷ 27 = cubic yards: 100 × 0.8889 = 88.89 cubic feet, ÷ 27 = 3.29 cubic yards in the trench. Waste goes on last, on that figure: × 1.1 = 3.62 cubic yards to order, which the plant rounds to 3.75 because ready-mix is sold by the quarter yard. Bags come from the waste-inclusive cubic feet: 97.78 ÷ 0.60 = 162.96, rounded up to 163 bags of 80 lb. Area does not enter a footing calculation at all, which is why a building's square footage from the square footage calculator is no help here; the perimeter is.
Footing width and thickness by soil: IRC 2021 Table R403.1(1) for light-frame construction
The code sizes a light-frame house footing by three things, the soil's bearing value, the number of storeys with their foundation type, and the roof load, and prints the answer as width × thickness in inches. R403.1.1 sets the floor first: The minimum width, W, and thickness, T, for concrete footings shall be in accordance with Tables R403.1(1) through R403.1(3) and Figure R403.1(1) or R403.1.3, as applicable, but not less than 12 inches (305 mm) in width and 6 inches (152 mm) in depth. The footing width shall be based on the load-bearing value of the soil in accordance with Table R401.4.1. Any chart that prints 8 in or 10 in widths is older than that sentence; the 1995 one-and-two-family code some pages still reproduce went down to 6 in on strong soil, and it cannot be used under the 2021 IRC.
The full light-frame table follows, all four load blocks, from the 2021 Seattle Residential Code print of the IRC, Chapter 4 pages 4-3 and 4-4. Read across to your soil column, down to your storey and foundation row, in the block for your roof live load or ground snow load. At 2,500 psf and above only seven cells are wider than the 12 × 6 minimum, six of them in the three-storey-plus-basement rows or the 70 psf block, and at 3,500 and 4,000 psf every cell is 12 × 6; thickness leaves 6 in only in the heaviest cells, 21 × 7, 22 × 7 and, at 1,500 psf under three storeys with a basement, 24 × 8.
| Story and type of structure | 1,500 | 2,000 | 2,500 | 3,000 | 3,500 | 4,000 |
|---|---|---|---|---|---|---|
| 1 story, slab-on-grade | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 1 story, with crawl space | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 1 story, plus basement | 16 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 2 story, slab-on-grade | 13 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 2 story, with crawl space | 15 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 2 story, plus basement | 19 × 6 | 14 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 3 story, slab-on-grade | 16 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 3 story, with crawl space | 18 × 6 | 14 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 3 story, plus basement | 22 × 7 | 16 × 6 | 13 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| Story and type of structure | 1,500 | 2,000 | 2,500 | 3,000 | 3,500 | 4,000 |
|---|---|---|---|---|---|---|
| 1 story, slab-on-grade | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 1 story, with crawl space | 13 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 1 story, plus basement | 16 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 2 story, slab-on-grade | 13 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 2 story, with crawl space | 16 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 2 story, plus basement | 19 × 6 | 14 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 3 story, slab-on-grade | 16 × 6 | 14 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 3 story, with crawl space | 19 × 6 | 14 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 3 story, plus basement | 22 × 7 | 16 × 6 | 13 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| Story and type of structure | 1,500 | 2,000 | 2,500 | 3,000 | 3,500 | 4,000 |
|---|---|---|---|---|---|---|
| 1 story, slab-on-grade | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 1 story, with crawl space | 14 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 1 story, plus basement | 18 × 6 | 13 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 2 story, slab-on-grade | 15 × 6 | 13 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 2 story, with crawl space | 17 × 6 | 13 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 2 story, plus basement | 21 × 7 | 15 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 3 story, slab-on-grade | 18 × 6 | 13 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 3 story, with crawl space | 20 × 6 | 15 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 3 story, plus basement | 24 × 8 | 18 × 6 | 14 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| Story and type of structure | 1,500 | 2,000 | 2,500 | 3,000 | 3,500 | 4,000 |
|---|---|---|---|---|---|---|
| 1 story, slab-on-grade | 14 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 1 story, with crawl space | 16 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 1 story, plus basement | 19 × 6 | 14 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 2 story, slab-on-grade | 17 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 2 story, with crawl space | 19 × 6 | 14 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 2 story, plus basement | 22 × 7 | 17 × 6 | 13 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 3 story, slab-on-grade | 20 × 6 | 15 × 6 | 12 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 3 story, with crawl space | 22 × 7 | 16 × 6 | 13 × 6 | 12 × 6 | 12 × 6 | 12 × 6 |
| 3 story, plus basement | 24 × 8 | 19 × 6 | 15 × 6 | 13 × 6 | 12 × 6 | 12 × 6 |
The table's four notes matter as much as its cells. Note a: Linear interpolation of footing width is permitted between the soil bearing pressures in the table. Extrapolation is not permitted. Note b gives the basis: a 32 ft building width, 9 ft walls, an 8 ft basement wall, 15 psf roof and ceiling, 10 psf floor and 12 psf wall dead loads, 40 psf first floor and 30 psf upper floors, a clear-span roof with an interior bearing wall or beam at each floor. Notes c and d adjust for building width: Where the building width perpendicular to the wall footing is greater than 32 feet, the footing width shall be increased by 2 inches and footing depth shall be increased by 1 inch for every 4 feet of increase in building width, and the reverse decrease is permitted under 32 ft down to the 12 × 6 floor. A 40 ft wide house on a 12 × 6 cell is therefore 16 × 8, which is why the tool's defaults are 16 and 8 rather than 12 and 6: they are the default, not a recommendation for your site.
Why this calculator does not size the footing
Because the soil column is the one input nobody can read off a plan. R401.4.1 lets the presumptive values of Table R401.4.1 stand in for a geotechnical report, quoted in the code section, but note b to that table hands anything under 1,500 psf to a soils investigation, and the building official can require a test wherever expansive, compressible or shifting soil is likely. A calculator that picked 12 × 6 on a guessed 2,000 psf would be wrong on exactly the sites where the width matters. So the width is a field with the table beside it, and brick veneer or a concrete wall change the table: R403.1(2) for brick veneer or lath and plaster runs to 32 × 12, R403.1(3) for cast-in-place concrete or partially grouted masonry walls to 34 × 13. One printed quirk for anyone checking the book: the 2021 Seattle print of Table R403.1(2) shows a 1 story plus basement cell at 50 psf and 1,500 psf as 20 × 60, where the pattern of the table reads 20 × 6. Both veneer and masonry tables are laid out in concrete footing and slab code.
Footing depth vs footing thickness: frost line, the 12 in rule and frost-protected footings
Two words get swapped on every job site and on half the calculator pages read for this one. Thickness is the concrete section the tool multiplies, 6 in minimum and 8 in by default. Depth is how far below the ground the bottom of that section sits, and it is a placement rule, not a volume: R403.1.4 says Exterior footings shall be placed not less than 12 inches (305 mm) below the undisturbed ground surface, and R403.1.4.1 adds the frost rule, that foundation walls, piers and other permanent supports shall be protected from frost by one or more of the following methods: 1. Extended below the frost line specified in Table R301.2. 2. Constructed in accordance with Section R403.3. 3. Constructed in accordance with ASCE 32. 4. Erected on solid rock. and that Footings shall not bear on frozen soil unless the frozen condition is permanent. The frost line itself is a number your jurisdiction enters in Table R301.2, which is why the tool prompts for it and never prints one.
The deep trench changes the volume only if you fill it with concrete. A footing set 42 in down in a frost climate is usually an 8 in footing with a foundation wall or a stem wall on top of it, and the wall is figured separately; the run and section in this tool are the footing alone. Where the whole trench is poured solid, a fence-post style trench footing, enter the trench depth as the thickness and the tool will treat it as one block. Two exceptions in R403.1.4.1 drop the frost requirement entirely: free-standing accessory structures with an area of 600 square feet (56 m2) or less, of light-frame construction, with an eave height of 10 feet (3048 mm) or less, and 400 sq ft or less for other construction, which is why a small shed can sit on a shallow footing where the house next to it cannot. Deck footings have their own depth section, R507.3, worked on the deck footing size calculator.
Frost-protected shallow foundations: Table R403.3(1)
Method 2 is the frost-protected shallow foundation of R403.3, for a building kept at a monthly mean of 64 °F or more, and it replaces depth with insulation. The table gives the footing depth and the insulation by air-freezing index, the cumulative degree-days below 32 °F listed by county in Table R403.3(2): a footing can stop at 12 to 16 in where the frost line would otherwise send it to 4 ft. It is not for unheated porches, garages or carports, and it cannot attach to a basement or crawl space that is not kept at that temperature.
| Air-freezing index (°F days) | Minimum footing depth D (in) | Vertical insulation R-value | Horizontal insulation R-value, along walls | Horizontal insulation R-value, at corners |
|---|---|---|---|---|
| 1,500 or less | 12 | 4.5 | Not required | Not required |
| 2,000 | 14 | 5.6 | Not required | Not required |
| 2,500 | 16 | 6.7 | 1.7 | 4.9 |
| 3,000 | 16 | 7.8 | 6.5 | 8.6 |
| 3,500 | 16 | 9.0 | 8.0 | 11.2 |
| 4,000 | 16 | 10.1 | 10.5 | 13.1 |
The horizontal insulation widths, dimensions A, B and C of Figure R403.3(1), are 12, 24 and 40 in for an index of 2,500 and 3,000 and 24, 30 or 36 and 60 in above that; the R-values in the table assume the specific EPS and XPS grades named in note c. None of this changes the concrete: a 16 in deep frost-protected footing is entered here as a 16 in thickness if it is poured solid, or as its section if it is a footing under a stem wall.
Continuous footing, straight run or pad footings: which layout fits the job
Continuous is the perimeter footing under every exterior wall of a house, garage, addition or shop, the case R403.1 opens with: All exterior walls shall be supported on continuous solid or fully grouted masonry or concrete footings, crushed stone footings, wood foundations, or other approved structural systems, bearing on undisturbed natural soils or engineered fill. Give it the building length and width and it does the corner arithmetic. Straight run is for everything that is not a closed loop: an interior bearing-wall footing, a retaining or garden wall, a porch footing on three sides, the thickened edge across a garage door where one forum poster wanted a 12 × 12 in edge across the front of a 24 ft steel building only, 0.98 cubic yards with waste and 44 bags. Run the perimeter and the interior lines as two results and add them.
Pad footings carry one load each: a porch post, a steel column in a basement, a pier under a girder. R403.1.1 sizes them by tributary load: The size of footings supporting piers and columns shall be based on the tributary load and allowable soil pressure in accordance with Table R401.4.1; the beam load calculator works the tributary area and load, and dividing that load by the soil's bearing value gives the pad area a plan should show. R403.1.3.6 permits isolated plain concrete footings supporting columns or pedestals in one- and two-family dwellings of three storeys or less with stud walls, so an unreinforced pad is within the prescriptive code. The tool takes the pad size and count and prints each pad's volume before waste beside the total.
Monolithic slab with a turned-down footing
A monolithic pour puts the footing and the slab in one placement, with the slab edge turned down into a trench. The footing part is a straight run with the slab's perimeter as its length and the turned-down section as width and thickness; the slab itself goes on the concrete slab calculator and the two are added. One rural owner pricing a 1,320 sq ft shop had the slab figured and the edge forgotten; a member did it for him, 140 ft of 14 × 9 in edge = 122.5 cubic feet, 4.54 yards before waste, on top of the slab's sixteen, and told him to order at least twenty-one. Here that run is 4.99 yards with waste, a 5 yard line on the ticket. In Seismic Design Categories D0 to D2 the code adds reinforcement to that edge, R403.1.3.3: one No. 4 bar top and bottom, or one No. 5 or two No. 4 in the middle third; and interior footings cast with the slab go 12 in below its top, R403.1.3.4.
Deck footings are a different calculation
A deck post footing is sized from DCA 6 and the deck's tributary area, dug to the deck's own depth rule in R507.3, and usually poured in a round form; none of that is a rectangular trench. The deck footing size calculator gives the pad size, the post hole concrete calculator gives the concrete per hole with the post subtracted, and the deck beam span calculator sets the post spacing that fixes the count. The pad layout here still works for a square deck pad if the size is already on the plan.
Concrete for common footings at the tool's defaults
Every row is the calculator at its default 10 percent waste and 80 lb bags, so the figures are what it prints when the shape is typed in; change the waste and the row moves. Two things to read across. A 60 × 40 ft shop on a 24 × 12 in footing is 16.3 yards; the same 200 ft of run on a 16 × 8 in footing would be 7.24, so the section, not the perimeter, is where a footing order more than doubles. And four pad footings at 0.43 yards is a job for 20 bags, under the half-yard floor where the tool stops offering a ready-mix line at all.
| Footing | Run or pads | Section | Cu yd to order | 80 lb bags |
|---|---|---|---|---|
| House 30 × 20 ft, continuous | 100 ft | 16 × 8 in | 3.62 | 163 |
| Garage 24 × 24 ft, continuous | 96 ft | 16 × 8 in | 3.48 | 157 |
| Addition 40 × 30 ft, continuous | 140 ft | 20 × 10 in | 7.92 | 357 |
| Shop 60 × 40 ft, continuous | 200 ft | 24 × 12 in | 16.3 | 734 |
| Shed 12 × 12 ft at the code minimum | 48 ft | 12 × 6 in | 0.98 | 44 |
| Monolithic slab edge 24 × 36 ft | 120 ft | 14 × 9 in | 4.28 | 193 |
| Straight wall footing | 30 ft | 16 × 8 in | 1.09 | 49 |
| Thickened edge under a 24 ft door | 24 ft | 12 × 12 in | 0.98 | 44 |
| Four pad footings | 4 pads | 24 × 24 × 8 in | 0.43 | 20 |
| Six pier pads | 6 pads | 30 × 30 × 10 in | 1.27 | 58 |
Cubic yards and bags per linear foot of footing by section
The per-foot figures are exact arithmetic with no waste, width × thickness ÷ 144 for cubic feet per foot, then ÷ 27 for yards and 27 ÷ that for how many feet a yard fills. Multiply by your run and add your waste; a 16 × 8 in footing takes 0.8889 cubic feet a foot, 0.89 in the table, so 100 ft is 88.89 cubic feet and a yard covers about 30.4 ft of it. The bags column is the raw figure ÷ 0.60 cubic feet per 80 lb bag, before rounding.
| Section (W × T) | Cu ft per ft | Cu yd per ft | Ft per cu yd | 80 lb bags per ft |
|---|---|---|---|---|
| 12 × 6 in | 0.5 | 0.019 | 54 | 0.83 |
| 12 × 8 in | 0.67 | 0.025 | 40.5 | 1.11 |
| 16 × 8 in | 0.89 | 0.033 | 30.4 | 1.48 |
| 18 × 8 in | 1 | 0.037 | 27 | 1.67 |
| 20 × 8 in | 1.11 | 0.041 | 24.3 | 1.85 |
| 20 × 10 in | 1.39 | 0.051 | 19.4 | 2.31 |
| 24 × 10 in | 1.67 | 0.062 | 16.2 | 2.78 |
| 24 × 12 in | 2 | 0.074 | 13.5 | 3.33 |
Two sections that look close are not: 12 × 6, the code minimum, is 0.5 cubic feet a foot, and 24 × 12, wider and thicker than any light-frame cell, is 2, four times as much concrete for twice the width. Order by the section on the drawing, not by the footing you poured last time.
Ready-mix or bags for a footing, and what strength the code asks for
The default footing is 163 bags of 80 lb mix, which is 13,040 lb to carry, split and turn in a mixer, against one 3.75 yard line on a truck; the same 100 ft at 12 × 6 in is still 92 bags. The tool prints the ready-mix row only from half a yard up, because a plant will not send a truck for a quarter yard and printing 0.25 next to four pads is worse than printing nothing; below that the bag rows lead. Ready-mix is ordered in quarter-yard steps, so the 3.62 yard headline becomes 3.75 on the ticket, and a 1.09 yard wall footing becomes 1.25. The bags of concrete calculator runs the four bag sizes against any volume, the concrete yards calculator works the truck count and short loads, and the break-even by volume between the two is worked in bagged concrete vs ready-mix.
Whichever way it arrives, the code sets the concrete. Table R402.2 gives the minimum specified compressive strength at 28 days by location and weathering potential, and a footing is the first row, 2,500 psi in every climate; the strength climbs only for concrete that is exposed. Note c, which hangs on the severe-weathering column, makes footing concrete that will freeze and thaw during construction air-entrained, and note d sets that air content at 5 to 7 percent. A bag labelled 4,000 psi exceeds the footing minimum by a wide margin; a ready-mix order for a footing is written as 2,500 psi unless the plans or the weathering column say otherwise.
| Type or location of concrete construction | Negligible | Moderate | Severe |
|---|---|---|---|
| Basement walls, foundations and other concrete not exposed to the weather | 2,500 | 2,500 | 2,500 |
| Basement slabs and interior slabs on grade, except garage floor slabs | 2,500 | 2,500 | 2,500 |
| Basement walls, foundation walls, exterior walls and other vertical concrete work exposed to the weather | 2,500 | 3,000 | 3,000 |
| Porches, carport slabs and steps exposed to the weather, and garage floor slabs | 2,500 | 3,000 | 3,500 |
Rebar, anchor bolts and what the calculator leaves out
The tool counts concrete and nothing else, so three things on every footing drawing are outside it. Reinforcement. The prescriptive footing sections require steel only in Seismic Design Categories D0, D1 and D2, R403.1.3, where a concrete or masonry stem wall on a footing gets one No. 4 vertical bar hooked into the footing at 4 ft on centre and one No. 4 horizontal bar 3 to 4 in from the footing's bottom; elsewhere the bars in a house footing come from the plans or the local amendment, not from the model code. Cover is fixed wherever bars are used: Steel reinforcement in concrete cast against the earth shall have a minimum cover of 3 inches (75 mm), 1½ in for No. 5 and smaller in removable forms exposed to earth or weather. Bar count and weight are on the rebar calculator.
Anchorage. R403.1.6 puts the sill bolts in the wall or slab that sits on the footing, not in the footing itself: ½ in bolts at not more than 6 ft on centre, 7 in into the concrete, in the middle third of the plate, two per plate section with one within 12 in and at least seven diameters of each end; they can be set while the concrete is plastic. Slope and steps. R403.1.5 wants the top of the footing level and the bottom no steeper than 1 in 10, stepped where the grade changes more than that; a stepped footing is several straight runs at different elevations, each entered as a run here, and the vertical risers of the steps are short thick sections added the same way.
Seven ways a footing estimate goes wrong
Each of these was found on a published calculator page or in a forum thread while this page was researched, and each is a measurement or a definition rather than the multiplication. The first and fourth are the expensive ones: an outside-face perimeter adds a footing width to every side, and a monolithic slab figured from its area leaves the whole edge off the ticket. The second is the definition mix-up the depth section untangles. The third is the one an inspector will send back.
- Outside perimeter. The run is the centreline; corners are counted once.
- Depth for thickness. Frost depth is placement, thickness is volume.
- Old width chart. The 2021 floor is 12 × 6; charts with 8 in widths predate it.
- Missing turned-down edge. Run the slab and the edge as two results.
- In-place volume ordered. Waste on a trench pour is real; the tool adds 10 percent.
- Wrong divisor. 1,728 to cubic feet, 46,656 to cubic yards.
- One pad, not all pads. The count field multiplies; check the each-pad row.
| Mistake | Wrong | Right |
|---|---|---|
| Perimeter measured outside the wall | 2 × (31.33 + 21.33) = 105.33 ft for a 30 × 20 building | 2 × (30 + 20) = 100 ft on the centreline; 3.62 cu yd, not 3.81 |
| Depth entered as thickness | 42 in frost depth typed into an 8 in footing | Thickness = the concrete section; the trench depth is where it sits |
| Width from an old chart | 8 in wide footing from a 1995 table | R403.1.1: not less than 12 in wide and 6 in thick; Table R403.1(1) for your soil |
| Monolithic edge forgotten | 1,320 sq ft slab ordered at the slab volume | Add the turned-down edge: 140 ft × 14 × 9 in = 4.54 cu yd more |
| No waste on a trench pour | 3.29 cu yd ordered for the default footing | 3.62 with 10 percent; a footing poured to earth walls runs wider and deeper than the plan |
| Inch formula misremembered | ÷ 46,660 for cubic yards from inches | ÷ 46,656 = 12³ × 27; or ÷ 1,728 for cubic feet, then ÷ 27 |
| Pads counted once | One 24 × 24 × 8 pad figured, four dug | Each pad 0.1 cu yd before waste; four with waste = 0.43 cu yd, 20 bags |
What the IRC says about concrete footings, and what it leaves to your soil
Chapter 4 of the residential code carries every footing rule this page quotes, and the chain runs from the soil up. Table R401.4.1 supplies the presumptive load-bearing values the width table is entered with, in lieu of a complete geotechnical evaluation; its note b sends any site where less than 1,500 psf is likely to a soils investigation. A gravel subgrade is the 3,000 psf row, which is the figure the gravel calculator refers back to for stone under a footing.
| Class of material | Load-bearing pressure (psf) |
|---|---|
| Crystalline bedrock | 12,000 |
| Sedimentary and foliated rock | 4,000 |
| Sandy gravel and/or gravel (GW and GP) | 3,000 |
| Sand, silty sand, clayey sand, silty gravel and clayey gravel (SW, SP, SM, SC, GM and GC) | 2,000 |
| Clay, sandy, silty clay, clayey silt, silt and sandy siltclay (CL, ML, MH and CH) | 1,500 |
From the bearing value, R403.1 asks that footings accommodate all loads according to Section R301 and… transmit the resulting loads to the soil within the limitations as determined from the character of the soil, R403.1.1 fixes the 12 × 6 floor and the 2 in to T projection, Table R403.1(1) sizes the light-frame case, R403.1.4 and R403.1.4.1 place the footing below 12 in and below frost, R403.1.5 keeps its top level and its bottom under a 1 in 10 slope, and Table R402.2 sets the concrete at 2,500 psi. The code also allows a footing that is not concrete at all: R403.4.1 crushed stone footings under precast walls, plated in lifts of not more than 8 in, sized by Table R403.4, and permanent wood foundations on the gravel of R403.2. Those tables, the brick-veneer and masonry-wall footing tables, and the slab rules of R506 are laid out together in concrete footing and slab code; the drainage rule that finishes the job, a grade falling 6 in in the first 10 ft under R401.3, is on the slab page.
Which concrete calculator do you need?
Every concrete tool on this site starts from the same volume arithmetic; each one adds the input its job turns on. Use this page when the question is a footing under a wall, a building or a pier; move across when it is a post in a hole, a slab, a truck, a bag count or the size of a deck footing.
| Job | Use | What it adds |
|---|---|---|
| Footing under a wall, a building or a pier | This page | Perimeter from the building size, run, pads; R403.1 checks; bags and ready-mix |
| Post in a hole, sonotube, fence post | Post hole concrete calculator | Subtracts the post from the hole; bags per hole |
| Size of a deck post footing | Deck footing size calculator | DCA 6 footing size from tributary area and soil |
| Slab on the footing, or a monolithic slab | Concrete slab calculator | Thickness by use, base, joints; add the edge from this page |
| Any other shape, eight of them | Concrete calculator | Slab, footing, column, wall, curb, steps in one tool |
| Ready-mix order and trucks | Concrete yards calculator | Quarter-yard rounding, short loads, truck count |
| Bags of any size | Bags of concrete calculator | 80, 60, 50, 40 lb against any volume; per-yard bag counts |
| Bars in the footing | Rebar calculator | Bar count, lengths and weight |
| Stone under the footing | Gravel calculator | Yards and tons of base with compaction |
| Driveway, patio, shed pad | Driveway, patio, shed base | The slab and its base by use |
| Fence post depth and spacing | Fence post spacing, depth and height | Post questions with worked figures |
| All of them | Concrete calculators hub | Every concrete and base tool on the site in one place |
Concrete footing calculator FAQ
How much concrete do I need for a footing 100 ft long, 16 in wide and 8 in deep?
About 3.62 cubic yards to order, 163 bags of 80 lb mix, or a 3.75 cubic yard ready-mix line. The section is 16 ÷ 12 × 8 ÷ 12 = 0.89 square feet; times 100 ft is 88.89 cubic feet, 3.29 cubic yards in the trench; the tool's 10 percent waste takes the order to 3.62. Two suppliers a yard apart on the same footing are usually one figuring the trench and one figuring the order, so ask which the number is. The calculator prints both, and the per-foot table above gives 0.89 cubic feet for every foot of a 16 × 8 in footing.
How do I calculate concrete for a perimeter footing around a house?
Add the building length and width, double it, and multiply by the footing width and thickness in feet, then divide by 27. A 30 × 20 ft house is 2 × (30 + 20) = 100 linear ft of footing measured along the footing's centreline; each corner belongs to two walls and is counted once. Measuring around the outside face of the footing instead gives 105.33 ft and over-orders by about 5 percent; measuring the inside face under-orders by the same. Interior bearing walls and a garage-door thickened edge are separate straight runs added on. The continuous layout in the tool does all of it from the two building dimensions.
Is footing depth the same as footing thickness?
No. Thickness is the height of the concrete section, 6 in minimum under R403.1.1 and 8 in by default here, and it is one of the three numbers the volume comes from. Depth is where the bottom of that section sits below the ground, at least 12 in below the undisturbed surface under R403.1.4 and below the local frost line under R403.1.4.1, and it changes the digging, not the concrete, unless the trench is poured solid. A footing in frost country is usually the footing section at the bottom of a deep trench with a wall on top; enter the footing, and figure the wall on its own.
How wide and thick does a concrete footing have to be?
At least 12 in wide and 6 in thick, and wider on weak soil or under more storeys, by Table R403.1(1). The table is printed in full above: a one-storey slab-on-grade house on 2,000 psf soil is 12 × 6 in every load block, a two-storey house with a basement on 1,500 psf soil under a 20 or 30 psf load is 19 × 6, and three storeys with a basement on 1,500 psf soil under a 50 or 70 psf snow load is 24 × 8. Brick veneer and masonry walls use Tables R403.1(2) and R403.1(3), which run wider. Three trades quoting three sizes for one shed is common; the table settles it.
How much concrete for deck footings and posts?
A deck post footing is a round hole or a sized pad, not a trench, so it is figured per hole on the post hole concrete calculator and sized on the deck footing size calculator; the volumes for 4x4 and 6x6 posts by depth are worked in concrete for footings and posts.
What is a concrete footing size rule of thumb?
The only rule of thumb worth using is the code floor, 12 in wide by 6 in thick, projecting 2 in past each face of the wall and no more than its own thickness; everything wider comes from the soil bearing value and the storey count in Table R403.1(1), which is a lookup, not a guess. The old trade rule of twice the wall width gives 16 in under an 8 in wall, the tool's default and a width the table reaches at 1,500 psf, but it is not the code and it is short on clay under a basement. Read the table for your soil column, interpolating if your report lands between two.
How deep do footings need to be below grade?
Not less than 12 in below the undisturbed ground surface, and below the frost line your jurisdiction lists in Table R301.2, unless the footing is frost-protected by insulation under R403.3, built to ASCE 32, or set on solid rock. That frost figure is local and the calculator does not print one. Free-standing accessory buildings of 600 sq ft or less in light frame, or 400 sq ft in other construction, with eaves of 10 ft or less, are exempt from the frost rule. The depth is placement; the thickness in the tool is the concrete section, so a 48 in frost depth does not become a 48 in footing unless the trench is poured solid.
What is the difference between a footer and a footing?
Nothing. Footer is the regional and trade word, footing is the code word, and Chapter 4 of the IRC uses footing throughout: R403.1 general, R403.1.1 minimum size, R403.1.4 minimum depth. Concrete suppliers and forum threads say footer, plans and inspectors say footing, and the calculator answers either. The same is true of pad, spread and isolated footing, three names for the single footing under a post or column, and of strip and continuous footing, two names for the one that runs under a wall. What matters on the order is the run, the width and the thickness, whatever the trench is called.
How many bags of concrete do I need for a footing?
Waste-inclusive cubic feet divided by the yield of the bag, rounded up: 0.60 cubic feet for 80 lb, 0.45 for 60 lb, 0.375 for 50 lb and 0.30 for 40 lb. The default 100 ft footing at 16 × 8 in is 97.78 cubic feet with waste, so 163 bags of 80 lb or 218 of 60 lb, over 13,040 lb to mix by hand; a 30 ft wall footing of the same section is 49 bags, and four 24 × 24 × 8 in pads are 20. The tool prints all four sizes under every result. Above a yard or so the ready-mix row is the practical answer.
How much concrete for a monolithic slab with a turned-down footing?
The slab plus a straight run for the edge. Figure the slab on the slab calculator, then enter the slab's perimeter as a straight run here with the turned-down section as width and thickness, and add the two. A 24 × 36 ft mono slab with a 14 × 9 in edge is 120 ft of run, 4.28 cubic yards with waste on top of the slab; the 1,320 sq ft shop in one forum thread had 140 ft of the same section, 4.54 yards before waste, that the owner had left off entirely. In Seismic Design Categories D0 to D2 the edge carries the No. 4 bars of R403.1.3.3.
Does a concrete slab need footings?
A slab that carries walls does; a slab that carries only itself and what sits on it does not. R403.1 requires every exterior wall to bear on a continuous footing, so a house, a garage or a shed with bearing walls has a footing under the wall line, either separate or turned down from a monolithic slab. A patio, a driveway or a shed pad with nothing framed on it is a slab on grade under R506 with no footing at all, and it is figured on the slab calculator. Where the slab is below grade R506.2.2 asks for a 4 in base; where it is not, the base is trade practice.
What PSI concrete for footings?
2,500 psi at 28 days in every weathering zone, by Table R402.2, which lists basement walls, foundations and other concrete not exposed to the weather at 2,500 under negligible, moderate and severe weathering alike. Exposed vertical work goes to 3,000 in moderate and severe zones and exposed flatwork such as porches and garage floors to 3,000 and 3,500, but a footing sits below grade and stays at the base figure. In the severe-weathering column note c makes footing concrete that freezes and thaws during construction air-entrained, at 5 to 7 percent air under note d. Your plans or an engineer can specify more; the code does not.
How much concrete do I need for footings?
Run × width × thickness in feet ÷ 27, plus waste, then bags or a quarter-yard truck line; the tool does all of it for a perimeter, a run or a set of pads. The per-post and per-footing worked figures are in concrete for footings and posts.
Do concrete footings need rebar?
Under the prescriptive code, only in Seismic Design Categories D0, D1 and D2, where R403.1.3 puts a hooked No. 4 vertical bar at 4 ft on centre and a No. 4 horizontal bar near the bottom of the footing under concrete or masonry stem walls, and No. 4 top and bottom bars in a turned-down slab edge. Elsewhere the code sets no footing steel for a light-frame house, and R403.1.3.6 permits plain isolated footings under columns; any continuous bars a crew places come from the plans or a local amendment. Wherever bars go in, cover against earth is 3 in. The calculator counts concrete only; the rebar calculator counts the bars.
How much waste should I add to a footing, and why more than a slab?
The tool adds 10 percent, which is about right for a footing formed with boards and low for one poured to the trench. A slab is formed on four sides and screeded to a known thickness; a trench footing is only as accurate as the bucket that dug it: a cleaned-up trench runs an inch or two wider than the plan width and its bottom is rarely dead level, so the concrete that fills those extras is the waste. On the default footing 10 percent is 0.33 of a yard, the difference between 3.29 in the trench and 3.62 ordered, and it is less trouble than a second truck.
Can I pour the footing and the wall at the same time?
Yes, where the plans allow a monolithic footing and stem wall, and the concrete is then two volumes added together: the footing section times its run from this page, plus the wall thickness times its height times the same run, which the concrete calculator's wall shape or the slab calculator can give. A single pour removes the construction joint between footing and wall, the joint R403.1.3.1 ties with hooked No. 4 bars in seismic zones, and it consolidates two short loads into one order. The projection rule still applies: the footing must stand 2 in past the wall on each side and no more than its thickness.
Source and verification of these footing figures
Every cubic-yard, cubic-foot, bag and per-foot figure on this page is regenerated from the same arithmetic the calculator runs, run × width ÷ 12 × thickness ÷ 12 ÷ 27 with the waste on the purchased quantity only, and checked by script against the copy before publishing; if a number here disagrees with the tool at the same inputs, the tool is right and the page has a typo. No footing width is recommended for any site: 16 × 8 is the tool's default and the page says so wherever it appears. Every code sentence is quoted from the 2021 Seattle Residential Code print of the IRC, Chapter 4, which prints the model code text with the city's amendments marked; the sections used are R401.3, R401.4.1 and Table R401.4.1 (page 4-1), Table R402.2 (4-2), R403.1 and R403.1.1 with Table R403.1(1) (4-3 and 4-4), the Table R403.1(2) cell noted above (4-5), R403.1.3.3 to R403.1.3.6 (4-10 and 4-11), R403.1.4, R403.1.4.1, R403.1.5 and R403.1.6 (4-11 and 4-12), R403.3 with Table R403.3(1) (4-14 to 4-16) and R403.4.1 (4-23). Seattle's own local amendments in that chapter are marked [S] in the print and none is used here. Deck footing depth and size come from R507 and AWC DCA 6 and are not quoted on this page. How every table on this site is checked is on the methodology page.
Built and maintained by Syed Zulqarnain.